Bi Weekly

CORPORATE UPDATES

2013
January 13, 2013 - Lluvia de Oro mine site visit to review new initiatives aimed at improving gold recovery operations and strategy to ramp up the mining rate in 2013 with the new site management team.

2012
October 17, 2012 - Mining continues at Lluvia de Oro in the Creston Pit and mining of the La Jojoba deposit has commenced. NWM is projecting 20-25,000 oz. Au production in 2012 and is expecting to ramp up in 2013.

2011
November 18, 2011 - This report is an update covering the past two weeks (November 5th to November 18th) of mining and construction activities at the Lluvia de Oro/ La Jojoba mine site in Sonora, Mexico.
November 04, 2011 - This report is an update of the past two weeks (October 24th to November 4th) of the mining and construction activities at the Lluvia de Oro/Jojoba mine site in Sonora, Mexico.
October 21, 2011 - This report is an update of the past two weeks (October 8th to October21st) of the mining and construction activities at the Lluvia de Oro/Jojoba mine site in Sonora, Mexico.
October 7, 2011 - This report is an update of the past two weeks (Sept 23rd to October7th) of the mining and construction activities at the Lluvia de Oro and Jojoba mine site in Sonora, Mexico.
September 23, 2011 - This report is an update of the past two weeks (Sept. 12th to Sept. 23rd) of site activities at the Lluvia de Oro and Jojoba mine site in Sonora, Mexico.
September 9, 2011 - The exploration department is working on the organization of the new drilling program scheduled to begin in October, in the Lluvia de Oro and La Jojoba areas of the mine site.
August 26, 2011 - During the first part of August the exploration department began to plan a new drilling program scheduled to begin in October, in the Lluvia de Oro and La Jojoba areas of the mine site.
May 25, 2011 - The Exploration Department has completed a drilling program at Campamento and has moved the diamond drill to concentrate on exploration of the Gold Ridge target at Lluvia de Oro

January 14, 2011 - The New Year starts where we left off last year: drilling and blasting in three different parts of the Creston Pit

2010
December 22, 2010 - Lluvia de Oro/La Jojoba Project The Mexican staff and the exploration, mining and construction crews at Lluvia de Oro have made great progress in 2010...more